EnviroNZ Waste Collection Facility Great South Road

882 Great South Road is a 13,000m2 commercial development in Penrose for EnviroNZ. Terra delivered Earthworks, Drainage, Rock Breaking, and Pavement construction. The drainage works and associated rockbreaking was very challenging, with all drainage works requiring it. We worked with the client to value engineer to combine trench profiles and cuts, reduce budgets and achieve savings whist still delivering on time.
Project type
Commercial Development
Date
2025
Location
Penrose, Auckland
Key Challenges - Rock Breaking
The project was unlaid by rock and the deep drainage required a huge amount of rockbreaking and disposal offsite. Terra worked with the engineer to combine service trench and drainage lines to reduce volumes, and created efficient production trains to maintain program.
Key Challenges - Uncontrolled Fill
Despite being underlaid by rock, there was a huge amount of uncontrolled fill used to fill the old yard over the years. We worked closely with the Geotechnical engineer Initia to limit the size of undercuts using geotextiles to overcome some requirements.
Key Challenges - Live Asbestos Wastewater Replacement
Watercare introduced a late requirement to replace an existing asbestos wastewater line through the site. This brought on numerous challenges with asbestos removal procedure at the same time as diverting live wastewater flows and building the new line. Terra managed these aspects together to delivery an cost effective outcome for the client.