The Park Homes Subdivision
Park Estate is a residential subdivision project delivering 109 lots. Terra delivered all civil works for the subdivision, including Earthworks, Drainage, Utilities, Pavements and Landscaping. All works were completed under an EPA and Auckland Council standards. Earthworks involved bulk imported cleanfill, preloading and retaining walls.
Project type
Residential Subdivision
Date
2024 - ongoing
Location
Papakura, Auckland
Key Challenge - First Gas Transmission Line
All works required works over and standover with First Gas, including exposing the length of Gas Main, assisting First Gas with recoating and backfilling.
Key Challenge - Imported Fill
Works are within a flood plain and all levels had to be raised. Terra imported 20,000m3 of clay fill for build up house platforms
Key Challenge - Stream Crossing
4m x 2.5m box culvert crossing a live stream with approved streamworks methodology. Installation was through peat, including excavation and removal of Kauri stumps.